Shanxi Pipeline Project completed successfully
--Hanzhong pipeline pigging, pressure test and drying project
Hanzhong project department has initiated the first pressure test stage since November 26, 2016 and with all the staff actively work, all the pipeline pigging and pressure test completed successfully on January 15,2017.
The department took charge of pigging, pressure test and drying work of stage II (LL426-LL751) Mianxian to Kangxian two gas transmission pipeline project. Under the leadership of the manager Bian Ruikai, the staff overcomes the rout fall head (500m-600m), more pressure test points, large coverage, long distance, snowy weather and other negative factors, actively organized, scientific construction, resolutely implement the management requirements of the project department, sincerely cooperate, efficiently completed all pipeline pigging and pressure testing work.
To ensure the pipeline strength and tight pressure test completed on schedule, Hanzhong Project department often worked day and night, took turns on duty, stick to their posts, due diligence, and made a positive contribute for the pipeline commissioning on schedule.
Hanzhong project working site
Pigging acceptance
|