Pipeline commissioning gets the owner’s reputation
 

    Xinjiang east three towns natural gas pipeline is about 208 kilometers long, the design pressure is 6.3 MPa. The pipeline is used L415 grade steel pipe, line pipe diameter is DN323.9, the branch line is DN219, and pressure is 6.3 MPa. Pipeline mainly lies along the village road, the gobi desert or S302, S303 provincial highway, and crossing four counties Fukang, Jimusar, Qitai and Mulei. On October 22, 2014, our company is authorized by Jiangsu Province Industrial Equipment Installation Group Co., LTD., to contract the project, and work for the pipeline and plant pigging, pressure testing, dry, replacement and commissioning. During the project commissioning, our employees overcome many difficulties such as short time and complex task, completer the task by safety, high efficiency and high quality successfully, and get the high praise of contractor and owner.

Xia Zhenyang, project manager of pipeline commissioning branch

Henan Zhongtuo Petroleum Engineering Technology Co.,Ltd


Previous: Wuhan Crossing Dragging Pipeline Successfully
Next: Shipping for Thailand Crossing Project

  
About us /  Customer service / Contact us Copyright ? 2010 Henan ZhongTuo Petroleum Engineering Technology Co.,Ltd All rights reserved
豫ICP備05002509號(hào)